Abstract: In order to determine a better solution for composite lining design of heavyhaul railway tunnels, the composite lining structure design of a singletrack heavyhaul tunnel on the Menghua railway is optimized and analyzed by using a field test and a numerical simulation method. The concrete and the grid steel frame are monitored and measured using embedded strain and stress gauges in the lining structure of the test section. The tunnel excavation support process is simulated using finite element software. In addition, the deformation and the internal force of the primary support structure under different working conditions are analyzed to evaluate the structural safety. The results show that: when the singletrack tunnel in Grade Ⅳ surrounding rock is constructed, (1) using the bench method, the crown moves upward before the primary support is closed; (2)the internal force of the primary support is mainly the axial force (pressure); (3) the corresponding bending moment shared by the shotcrete and the steel frame is relatively small, accounting for approximately 70% to 90%; and (4) the densification of the steel grid truss reduces the shotcrete load proportion and improves its safety.
Key words: heavy-haul railway tunnel, composite lining, numerical simulation, monitoring measurement, bench method, lining optimization
CLC Number:
U 45
MEI Zhu. Optimization of Composite Lining Structure of a SingleTrack HeavyHaul Railway Tunnel[J]. Tunnel Construction, 2021, 41(9): 1547-1554.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.2096-4498.2021.09.014
http://www.suidaojs.com/EN/Y2021/V41/I9/1547
Rockburst Mechanism of Daxiagu Tunnel in Horizontal Rock Formation with High Crustal Stress
Study on Rationality of Modified Construction Method of Urban Tunnel Portal under Loose Deposits
Protection Technology of Railway Shield Tunnel Underpassing New and Old Highway Bridge Piles: a Case Study on GuangzhouFoshan Intercity
Underpassing FoshanKaiping Highway Bridge Piles
Construction Risk Control of a Metro Shield Tunnel in a Curved Receiving Section Obliquely Crossing an Adjacent Existing Station: a Case Study on Nanning Rail Transit Line 5 Crossing underneath Guangxi University Station on Existing Line 1
Scheme and Deformation Control of a Large CrossSection Flat Roofed Station Spanning Beneath Existing Buildings:
a Case Study of Phase Ⅲ Qianmen Station Project of Beijing Metro Line 8
Construction Mechanics of Transition Connection between a SingleSpan
FiveLane Highway Tunnel and Small ClearDistance Tunnel with
ThreeLane Main Tunnel and TwoLane Ramp
Analysis of SurroundingRock Disturbance Caused by TBM Excavation of Deepburied Railway Tunnel