Construction Scheme and Mechanical Properties of a Prefabricated Metro Station Constructed by TwinTube Closely Spaced PipeJacking Method

CHEN Xiangsheng1, 2, 3, 4, WANG Lei1, YANG Wensheng5, SU Dong1, 2, 3, *  WU Yongzhao5, LIU Shuya4, 5   

  1. (1.College of Civil and Transportation Engineering,Shenzhen University,Shenzhen 518060,Guangdong,China;2.Key Laboratory of Coastal Urban Resilient Infrastructures (MOE),Shenzhen University,Shenzhen 518060,Guangdong, China;3.Shenzhen Key Laboratory of Green, Efficient and Intelligent Construction of Underground Metro Station,Shenzhen 518060,Guangdong, China;4.Shenzhen Metro Group Co.,Ltd.,Shenzhen 518026,Guangdong,China;5.Shenzhen Municipal Design & Research Co., Ltd.,Shenzhen 518029,Guangdong,China)

  • Online:2023-07-20 Published:2023-08-06

Abstract:

A case study is conducted on the Shasan station of the Shenzhen metro line 12 to realize the construction of a largecrosssection prefabricated metro station using a smallcrosssection pipejacking machine. In addition, the construction scheme and mechanical properties of the station constructed by the twintube closely spaced pipejacking method are investigated. First, the structural design concept of this novel method is presented, including the crosssection division and structural transformation of the station along with construction procedures. Furthermore, the transformation method for the vertical and transverse force system and the construction processes for transforming the twintube substructure into the integral station structure are proposed based on the characteristics of the proposed construction method and the station structure. Second, the segmentation of the ring substructure, structural joint design, and waterproof system design are introduced. Finally, the variation law of the bending moment of the station structure during the construction process is analyzed by a threedimensional finite element model established using the finite element software ABAQUS and based on the loadstructure method. The study shows that the peak values of the bending moments of the left and rightline substructures of the station slightly change during the construction process, demonstrating the rationality of the construction procedure. Meanwhile, the bending moments of the left and rightline substructures vary due to the asymmetric design of the joint position and different boundary conditions during construction. Therefore, the bending momentcontrolling section should be carefully considered in the design of the station structure.

Key words:

 , twintube closely spaced rectangular jacking pipes, prefabricated metro station, joint, structural design, structural transformation, waterproof design, force analysis