Analysis on and Control of Settlement in Metro Construction

JIA Jian-Jun,  Zhang-Ding-Li,  Wang-Meng-Shu,  Zhang-Cheng-Beng   

  1. 1. Tunnels and Underground Works Research &|Test Center of Beijing Jiaotong University2. China Railway Tunnel Group Co., Ltd
  • Received:2005-08-26 Revised:2006-01-13 Online:2006-02-20 Published:2010-01-26

Abstract:

On basis of the results of the monitoring and measurement of Huangzhuang station of line No. 4 and No. 10 of Beijing Metro, the article summarizes the reasons and regular pattern of ground surface settlement and crown subsidence of Huangzhuang station of line No. 4 of Beijing Metro constructed by shallowburied undercutting method, and presents relevant countermeasures to control the settlement. The article can provide guidance for the construction of similar works in the future.