Countermeasures for Tunnel/shaft Construction in Water
bearing Sand Layers: Case Study on Beijing Metro

ZHANG Guo-Liang,  Wang-Jian-Cheng   

  1. Beijing Tunnel Construction Co., Ltd. of China Railway Tunnel Group
  • Received:2006-04-17 Online:2006-06-20 Published:2009-12-09

Abstract:

 On basis of the construction of Ciqikou~Chongwenmen running tunnel and Chongwenmen station of Beijing Metro, the article presents the schemes of the constructions in waterbearing sand layers for the intermediate temporary shaft and cross tunnel of the running tunnel and the southeast ventilation shaft and ventilation tunnel of Chongwenmen station. The article also presents the countermeasures for the prevention of water/sand inflow so as to avoid serious subsidence. The article emphasizes on the different dewatering measures taken according to different geological conditions.

Key words: waterbearing sand layer construction countermeasure  , blind area of dewatering