ISSN 2096-4498
CN 44-1745/U
Tunnel Construction ›› 2006, Vol. 26 ›› Issue (6): 84-86.DOI: B
• wenzhang • Previous Articles Next Articles
SHU Yang-Hui
Received:
Revised:
Online:
Published:
Abstract:
The paper presents the construction methods and corresponding machinery matching schemes adopted in each construction stage of exit portion of Yuanliangshan tunnel. On basis of summary of the power capacity of the major electric equipment inside the tunnel, the paper describes the electric matching scheme and the arrangement of the power supply equipment. Finally, regarding the defects in the matching of the machinery and equipment, the paper provides some modification recommendations.
CLC Number:
U455.3
SHU Yang-Hui. Machinery Matching and Power Supply Applied in Construction of Exit Portion of Yuanliangshan Tunnel[J]. Tunnel Construction, 2006, 26(6): 84-86.