Abstract:
Taking Jinjishan tunnel as project case, the paper expatiates on the waterproofing and drainage measures taken during the tunnel lining construction. The paper provides detailed description of the construction methods for the plastic drainage blind ditches, drainage systems of the short side walls, waterproofing membranes, watersealing strips for the construction joints and settlement joints, the secondary lining and the crown grouting. The paper also recommends some items to which special attention should be paid during construction and provides some new construction concepts.
CLC Number:
U455
TAO Li-Zhen. Waterproofing and Drainage Construction Technology for Lining of Jinjishan Tunnel[J]. Tunnel Construction, 2007, 27(3): 105-107.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2007/V27/I3/105