Key Construction Technologies and Countermeasures for
Largescale Mined Interchange Metro Stations

 CHEN Chao, DONG Xiao-Long   

  1. Shenyang Metro Headquarter
  • Received:2007-05-10 Revised:2007-06-07 Online:2007-06-20 Published:2009-12-04

Abstract:

Taking the construction of Youth Street Station of Shenyang Metro as case history, the author presents the major construction steps and key points of PBA (PileBeamArch) construction method. Due to the complex structure of the Metro station, PBA (PileBeamArch) construction method is adopted, which improves the safety and stability of the works, minimizes the deformation occurring during construction and protects the adjacent structures and buildings effectively.