The construction of the connection tunnels of the running tunnels of Metro works is one of the critical aspects of Metro works. The excavation of the pumping stations on the floors of the connection tunnels located in soft ground is of fundamental importance to the construction of the connection tunnels. Taking the construction of No. 2 pumping station of TianWu running tunnel on line 3 of Guangzhou Metro as case history, the authors present the application of the soil grouting consolidation method and mining method in waterrich soft ground.
CLC Number:
U455
LI Qi-Sen, Tun-Lei. Construction Technology for Pumping Station of TianWu Running Tunnel on Line 3 of Guangzhou Metro[J]. Tunnel Construction, 2007, 27(4): 82-84.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2007/V27/I4/82