The authors give a brief introduction to the Yellow River crossing project and the main operation modes of the slurry shield. The authors further provide detailed information on the assembly, launching, boring, segment erection, simultaneous grouting and the second launching of the slurry pressure balanced shield machine used for Yellow River crossing project. Finally, the authors make discussions on the boring construction in special section of the tunnel.
CLC Number:
 
U455.43
CA Hui, LI Rong-Zhi. On Shield Construction Technology for Yellow River Crossing Tunnel of Middle Line of SouthNorth Water Transferring Project[J]. Tunnel Construction, 2007, 27(6): 57-62.