XIAO Guangliang
Received:
Revised:
Online:
Published:
Abstract:
A shieldbored Metro tunnel in Shanghai crosses underneath the sensitive section of ShanghaiNanjing railway, therefore the railway authorities have strict requirements on the settlement of the railway tracks. Analysis is made on the risks of the shield tunneling across the existing railway by means of FEM and the following technical countermeasures are proposed: firstly, preconsolidation is made for the ground where the shield passes so as to improve the ground's stability; secondly, strengthened segments with preserved grouting holes are adopted in the tunnel design; thirdly, proper resources are allocated, the construction parameters are optimized and the construction monitoring and measurement are enhanced; finally, the shield tunneling is executed strictly following the predetermined plan. In the end, the shield crosses underneath the existing railway successfully. The paper can provide reference for similar works in the future.
Key words: shield machinesoft soil groundrisk analysispreconsolidationcrossing underneath existing railwaysettlement control  
CLC Number:
U455.43
XIAO Guangliang. Construction technology for Tunnel Boring Crossing underneath Existing Railway by Shield Machine in Soft Ground[J]. Tunnel Construction, 2008, 28(3): 324-329.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2008/V28/I3/324