Hyperbaric Operation of Shield in Cobble Stratum of Chengdu Metro

GUO Jia-Qiang, CHEN Kui   

  1. 1. China Railway Tunnel Joint Stock Co., Ltd2. Tunneling Equipment Manufacture Co., Ltd. of China Railway Tunnel Group
  • Received:2008-07-08 Revised:2008-08-22 Online:2008-10-20 Published:2009-11-25

Abstract:

Taking running tunnel of Provincial Stadium to South Railway Station of No.1 line of Chengdu Metro as an example, the authors introduce the methods and measures of hyperbaric operation in water bearing cobble stratum. Moreover, the authors bring forward the key technologies and methods of hyperbaric operation taken so as to ensure the stability and sealing performance of cobble stratum.