CPIII Control Points Survey Technology for Ballastless
Track of HighSpeed Railway

LENG Daoyuan   

  1. China Railway Tunnel Group Co., Ltd
  • Received:2008-12-29 Revised:2009-03-12 Online:2009-04-20 Published:2009-11-17

Abstract:

he ballastless track of highspeed railways should be of good stability, continuity and high evenness. High accuracy threedimensional control survey technology is needed in the construction of the ballastless track. Taking the survey practice in Feiluan Tunnel on WenzhouFuzhou Railway and Jiuniushan Tunnel and Fenghuangshan Tunnel on NingboTaizhouWenzhou Railway as example, the author presents the characteristics, technical requirements and survey method of CPIII control points survey technology for the ballastless track of highspeed railways and makes analysis on some survey errors.

CLC Number: