Taking the first largespace atrium Metro station in Nanjing, which is constructed by cut and cover method, as an example, the authors analyze the key factors that influence the design of the atrium structure, including the restriction effect of the structure composed by the remaining intermediate floor slabs and the intermediate columns on the side walls and the structural safety and stability of the intermediate columns under lateral displacement conditions. Furthermore, the authors also propose methods and measures that can be used as references for the design of similar projects in the future.
Key words: cut and cover method, Metro station, atrium structure, restriction effect, stability of intermediate column, design method
CLC Number:
U 231+.1
LIU Jun, SHEN Xiao-Wei. Analysis on Design of Atrium Structure of a Metro Station in Nanjing Constructed by Cut and Cover Method[J]. Tunnel Construction, 2009, 29(5): 531-534.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2009/V29/I5/531
Research and Application of Prefabricated Structure Construction Technology for Metro Station
Design Technology and Method of OpenCut Prefabricated Underground Structures of Urban Rail Transit
Mechanical Property Analysis of Top Arch Joint for Prefabricated Underground Metro Station Structure Based on Insuit Monitoring
Processing Quality Inspection and Installation Accuracy Prediction of Prefabricated Metro Components
Design Technology of Outdoor Fire Hydrant Systems in Underground Metro Stations
Support Scheme for Deep Foundation Pit of Metro Station with Connection Gallery in Soft Soil
Deformation Monitoring and Analysis of a New Composite Retaining Structure for Deep Foundation Pit of a Station Adjacent to a River
Comparative Study on Applicability of Normal Section Design Method for Steel FiberReinforced Concrete Segment
Settlement Control Technology in Metro Station Construction with Large Cross-Section Rectangular Pipe Jacking Method: a Case Study of
Jing′an Temple Station of Line No.14 of Shanghai Metro