Tunnel Construction ›› 2009, Vol. 29 ›› Issue (增刊2): 104-107.DOI: B

• wenzhang • Previous Articles     Next Articles

Machinery Matching and Construction Organization for Rapid Construction
of Inclined Shafts with Trackless Transportation System

WEI Penghua   

  1. The 3rd Engineering Co., Ltd. of China Railway Tunnel Group, Shenzhen 518051, Guangdong, China
  • Received:2009-06-29 Revised:2009-08-28 Online:2009-09-30 Published:2010-01-04

Abstract:

Based on the construction experience of No. 1 and No. 2 inclined shafts of Dananshan tunnel on XiamenShenzhen railway, the author, taking No. 1 inclined shaft of Dananshan tunnel as an example, analyzes the factors that have influence on the rapid construction of inclined shafts and summarizes the countermeasures. The author expounds on the reasonable organization forms, site management experience and type selection, matching principle, matching plan and matching calculation method of construction machinery under the condition of trackless transportation system. Finally, the author makes some comments on the mechanical tunneling and cooperation among the related parties. This paper can provide reference for the machinery matching and construction organization of similar inclined shafts in the future.

CLC Number: