Construction Technology for Removing Obstacle Piles along Shield-bored Tunnels by Impacting Method

CHEN Shi-Meng   

  1. (Xi'an Metro Co., Ltd, Xi'an 710018, China)
  • Received:2009-12-21 Revised:2010-01-20 Online:2010-02-20 Published:2010-05-11
  • About author:陈世明(1974—)|男|陕西人|1999年毕业于西北建筑工程学院(现长安大学)机械制造工艺与设备专业|本科|工程师|现从事地铁施工管理工作。

Abstract:

4 obstacle pile removing methods are compared, with the removing of the obstacle piles along the route of a shield-bored tunnel of Line 2 of Xi'an Metro as an example, and, in the end, the method of "foundation pit cutting and pile removing by impacting" is adopted. The key points and key technical measures of "pile removing by impacting method" are presented in the paper. The engineering practice demonstrates that the construction method adopted is simple, easy to execute, safe, reliable and time-saving. The experience can be served as reference for similar projects in the future.

Key words:  shield-bored tunnel, obstacle pile, pile removing by impacting method, technical control