DIAO Yi
Received:
Revised:
Online:
Published:
Abstract:
PPS is the guidance system for most of the TBMs imported to China in recent years. In this paper, the working principle of PPS guidance system is presented, the operation procedures and cautions during the installation of PPS guidance system are summarized, the management contents and maintenance measures of PPS guidance system are proposed, the detection technology and troubleshooting techniques for failures, such as system installation malfunctions, limitexceeding survey errors, obstructed vision for total station survey and malfunction of ranging board of total station, are summarized, with TBMbored waterdelivery tunnels as examples. The paper can provide reference for similar projects in the future.
Key words: TBM, PPS guidance system, system installation, management during construction, troubleshooting
CLC Number:
TV554.2
DIAO Yi. Application and Management of PPS Guidance System of TBM[J]. Tunnel Construction, 2010, 30(1): 63-66,96.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2010/V30/I1/63
Design and Analysis of a New TBM Propulsion System with Small Turning Radius
Dynamic Model and Vibration Analysis of TBM Edge Disccutter Based on MATLAB/Simulink