ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2010, Vol. 30 ›› Issue (2): 131-133,178.DOI: B

• wenzhang • Previous Articles     Next Articles

Comparison and Contrast between CRD Excavation
Method and 3bench 7step Excavation Method and Their Optimization

 CUI Xiao-Feng1, SUN Shao-Feng2, WANG An-Hong2, HOU Min1   

  1. 1. CCCC Second Highway Engineering Co., Ltd., Xi'an 710065, China;
    2. LanzhouChongqing Railway Co., Ltd., Lanzhou 730050, China
  • Received:2010-01-13 Revised:2010-03-25 Online:2010-04-20 Published:2010-05-25

Abstract:

CRD excavation method and 3bench 7step excavation method are compared, analyzed and evaluated in the paper. Furthermore, a new excavation method, i.e., bench method with core soil and temporary invert is proposed so as to enrich the tunnel excavation method.

Key words: CRD excavation method, 3 bench 7 step excavation method, bench method with core soil and temporary invert

CLC Number: