Tunnel Construction ›› 2010, Vol. 30 ›› Issue (2): 134-136.DOI: B
• wenzhang • Previous Articles Next Articles
XU Yong1, LIU Zhong-Ren2, WANG Wei-Gao2, KOU Jiang1
Received:
Revised:
Online:
Published:
Abstract:
Serious settlement, convergence and deformation always occur during the construction of doubletrack railway tunnels located in soft ground. 3bench 7step construction method, CRD construction method and enlargedarchfoot bench method are adopted in the construction of Liangshui tunnel on LanzhouChongqing railway. These three construction methods are compared in terms of safety, advance rates and equipment availability. It is concluded that enlargedarchfoot bench method is more suitable for the construction of doubletrack railway tunnels located in soft ground.
Key words: tunnel in soft ground, deformation control, monitoring, enlarged arch foot bench method
CLC Number:
U 455.4
XU Yong, LIU Zhong-Ren, WANG Wei-Gao, KOU Jiang. Comparison and Contrast among Different Construction Methods for Doubletrack Railway Tunnels in Soft Ground[J]. Tunnel Construction, 2010, 30(2): 134-136.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2010/V30/I2/134
Study on Key Technologies and Application of Engineering Big Data Management Platform of Tunnel Boring Machine