The deformation control method for large crosssection tunnels in mudstone ground is presented, with the construction of the entrance section of Hujiawan tunnel on LanzhouChongqing railway as an example. During construction, monitoring is executed to master the status of the rock mass deformation and temporary inverts and fanshaped supports are installed for the tunnel constructed by "top heading and bench" method so as to control the deformation. In the end, satisfactory results are achieved. The paper can be served as reference for the deformation control of the large crosssection tunnels on passengerdedicated railways.
Key words: mudstone ground, large cross section tunnel, deformation, control
CLC Number:
U 451+.2
ZHANG Xiu-Liang, DAN Guang-Rong, CHEN Jie-Hua, BO Ai. Case Study on Rock Mass Deformation Control of Large Crosssection Tunnels in Mudstone Ground[J]. Tunnel Construction, 2010, 30(2): 179-181.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2010/V30/I2/179