ISSN 2096-4498
CN 44-1745/U
Tunnel Construction ›› 2010, Vol. 30 ›› Issue (3): 276-280.
• wenzhang • Previous Articles Next Articles
DONG Yu-Guo
Received:
Revised:
Online:
Published:
Abstract:
In order to cope with F11 fault of Qiyueshan tunnel, freezing method and fullface curtain grouting method can be used. Unfortunately, both of the two methods have the disadvantage of long reinforcement period. The earlier tunnelingthrough of Qiyueshan tunnel, which is one of the control works of YichangWanzhou Railway, means that YichangWanzhou Railway can be put into operation earlier. Thus, the reinforcement period is one of the most important indexes in the selection of the proper reinforcement method. The original "column shape reinforcement mode" of curtain grouting is optimized into "bucket shape reinforcement mode". Due to the continuous technological optimization, the grouting mode aimed at sealing large fissure water and reinforcing the rock mass are developed and the reinforcement period is shortened.
Key words: grouting reinforcement, Qiyueshan tunnel, high pressure and rich water, fault, curtain grouting
DONG Yu-Guo. Study and Application of Grouting Reinforcement Technology in Coping with F11 Fault of Qiyueshan Tunnel[J]. Tunnel Construction, 2010, 30(3): 276-280.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/
http://www.suidaojs.com/EN/Y2010/V30/I3/276