Abstract:
The technology of roof ripping between large crosssectional inclined shaft (with the crosssectional area reaching 84.315m2) and main tunnel is presented, with the roof ripping construction between No. 1 inclined shaft and main tunnel of Baojiashan tunnel as an example. The construction scheme of advance reinforcement, sequential excavation, strengthened primary reinforcement, supporting immediately after excavation, timely ring closing and strengthened monitoring is established on basis of fully understanding of the geological conditions. The construction method for the connection section is focused. The construction experience is summarized. The paper can be served as reference for similar projects in the future.
Key words: tunnel, large cross section, inclined shaft, roof ripping
SHI Zhen-Yu. Technology of Roof Ripping Between Large CrossSectional Inclined Shaft and Main Tunnel: Case Study on Baojiashan Tunnel[J]. Tunnel Construction, 2010, 30(3): 313-316.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/
http://www.suidaojs.com/EN/Y2010/V30/I3/313
Key Technologies of Cutterhead Configuration and Cutter Replacement for Large diameter Shield under High Water Pressure
Experimental Effect Prediction of Ground Conditioning of Water rich Sandy Stratum Based on BP Neural Network
Fullscale Experimental Study on Bending Performance of Segmental Joints of Large Crosssection Shield Tunnel under Pure Compressive Bending Condition
Study on Optimization of Emergency Rescue Station of Yuntunbao Tunnel on ChengduLanzhou Railway
Launching and Receiving Technology of Large Crosssection Horseshoeshaped Shield Used in Baicheng Tunnel
Design and Analysis of a New TBM Propulsion System with Small Turning Radius
Study on Key Technologies and Application of Engineering Big Data Management Platform of Tunnel Boring Machine
Improvement Technology of Bearing Capacity of Prestressed Anchor Cable in Large span Tunnel: a Case Study on Badaling Great Wall Station