Abstract:
The existing formworks for invert casting have such disadvantages as high weight, difficult installation, complex invert construction procedure, difficult in onetime casting of the invert and the side wall foundation and high investment cost. Taking the construction of the exit section of Xiamao tunnel on XiangtangPutian Railway as an example, the author has developed a new arcshaped composite steel formwork after detailed studies, which has overcome the disadvantages of the existing formworks. Furthermore, the author presents the design and fabrication of the new formworks, as well as the fullbreadth casting of the invert with the new formworks.
Key words: high speed railway, tunnel, invert, new arcshaped composite steel formwork
Diao-An-Beng. Application of New Arcshaped Composite Steel formwork in Fullbreadth Construction of Invert of High Speed Railway Tunnel[J]. Tunnel Construction, 2010, 30(6): 706-711.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/
http://www.suidaojs.com/EN/Y2010/V30/I6/706
Key Technologies of Cutterhead Configuration and Cutter Replacement for Large diameter Shield under High Water Pressure
Experimental Effect Prediction of Ground Conditioning of Water rich Sandy Stratum Based on BP Neural Network
Fullscale Experimental Study on Bending Performance of Segmental Joints of Large Crosssection Shield Tunnel under Pure Compressive Bending Condition
Study on Optimization of Emergency Rescue Station of Yuntunbao Tunnel on ChengduLanzhou Railway
Launching and Receiving Technology of Large Crosssection Horseshoeshaped Shield Used in Baicheng Tunnel
Design and Analysis of a New TBM Propulsion System with Small Turning Radius
Study on Key Technologies and Application of Engineering Big Data Management Platform of Tunnel Boring Machine
Improvement Technology of Bearing Capacity of Prestressed Anchor Cable in Large span Tunnel: a Case Study on Badaling Great Wall Station