Construction Technology for Concrete Filled in Steel Pipe Columns

LI  Hai-Long   

  1. The 3rd Engineering Co., Ltd. of China Railway Tunnel Group, Shenzhen 518001, Guangdong, China
  • Received:2010-11-02 Revised:2010-11-22 Online:2011-01-13 Published:2011-01-05

Abstract:

Construction technology for C80 high performance concrete is presented, with the construction of the underground transfer structure and surface building of Laojie Station on line 3 of Shenzhen Metro as an example. The construction process of C80 high performance concrete filled in the steel pipe columns is presented. The indexes of C80 high performance concrete for the steel pipe columns are determined through insitu simulations and concrete mixing trials. In the end, problems imposed by the large quantity of long thin concretefilled steel pipe columns and complex working environment are solved, which guarantees the successful construction of the large underground Metro works and the surface building.

Key words: concretefilled steel pipe column, C80 high performance concrete, high order dropping, insitu vibrationfree simulation