ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2011, Vol. 31 ›› Issue (S2): 97-102.

• wenzhang • Previous Articles     Next Articles

Construction Technologies for Shallowburied and Mined Metro Stations

JIANG Chong   

  1. (The 4th Engineering Co., Ltd. of China Railway Tunnel Group, Nanning 530003, China)
  • Received:2011-08-02 Revised:2011-09-28 Online:2011-11-20 Published:2011-12-29

Abstract: In the construction of Gaoyijou station of Chongqing rail transit: the combination of concrete gatepost and I beam gate frame is adopted in the transition construction of construction tunnel into main station body; shock absorption is adopted in the main station body excavation; static blasting is used in the construction of the connected section of No. 2 ventilation tunnel and main station body, and the “connection first and concrete gatepost after” principle is made in lining construction. In the end, the rapid construction of shallowburied and mined tunnel with complex environment is guaranteed.

Key words: tunnel with large crosssection, shallowburied and mined Metro station, shock absorption, static blasting