Laying Methods for Waterproofing and Thermal Insulation Layers: Case Study on Tunnels in Cold Regions

LI Zhankui   

  1. (The 2nd Engineering Co., Ltd. of China Railway Tunnel Group, Sanhe 065201, Hebei, China)
  • Received:2011-11-07 Revised:2011-11-30 Online:2012-02-20 Published:2012-03-09

Abstract: The sandwich structure of double layers of waterproofing membranes, with one layer of thermal insulation board in between, is designed for Lafashan tunnel. 4 methods to lay the sandwich structure, including adhesion method, hanging method, circumferential rebar fixing method and connection strip tensioning method, are tried in the site. Comparison and contrast are made on these four methods. It is concluded that the connection strip tensioning method is the best method in terms of economy, environment protection, feasibility and practicability.

Key words: cold region, tunnel, waterproofing membrane, thermal insulation layer