ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2012, Vol. 32 ›› Issue (4): 514-517.DOI: 10.3973/j.issn.1672-741X.2012.04.015

• wenzhang • Previous Articles     Next Articles

Discussion on Rebar Calculation of Metro Station Constructed by Cut and Cover Method

SONG Yi   

  1. (China Railway Tunnel Survey & Design Institute Co., Ltd., Tianjin 300013, China)
  • Received:2012-02-09 Revised:2012-04-03 Online:2012-08-20 Published:2012-10-16

Abstract: The rebar calculation of Metro station constructed by cut and cover method is discussed. It is proposed that the peaktoaverage power reduction, axial force, haunch and distribution bar should be considered in the rebar calculation of Metro station. The proposal is helpful in improving the design quality and reducing the cost, if it is implemented in the design of Metro stations.

Key words: Metro station, cut and cover method, rebar design, power reduction, axial force, haunch distribution