Tunnel Construction ›› 2012, Vol. 32 ›› Issue (5): 705-708.DOI: 10.3973/j.issn.1672-741X.2012.05.017
• wenzhang • Previous Articles Next Articles
ZHAO Dongbo, LI Hongjun
Received:
Revised:
Online:
Published:
Abstract: The thicknesses of the concrete waterstopping wall and antishearing wall of Xiangshan tunnel are 7 m and 5 m respectively. Countermeasures, including reserving protection layer, drilling vibrationreducing hole, nonblasting pilot heading, strict control of the charging quantity of each interval and rational blasting parameter design, are taken in order to demolish the waterstopping wall and the antishearing wall and to ensure the safety of the lining. In the end, good result has been achieved.
Key words: tunnel, waterstopping wall, blasting demolition, vibrationreducing hole, pilot heading, nonblasting excavation
ZHAO Dongbo, LI Hongjun. Case Study on Blasting Demolition of Waterstopping Wall of Xiangshan Tunnel[J]. Tunnel Construction, 2012, 32(5): 705-708.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/ 10.3973/j.issn.1672-741X.2012.05.017
http://www.suidaojs.com/EN/Y2012/V32/I5/705
Key Technologies of Cutterhead Configuration and Cutter Replacement for Large diameter Shield under High Water Pressure
Experimental Effect Prediction of Ground Conditioning of Water rich Sandy Stratum Based on BP Neural Network
Fullscale Experimental Study on Bending Performance of Segmental Joints of Large Crosssection Shield Tunnel under Pure Compressive Bending Condition
Study on Optimization of Emergency Rescue Station of Yuntunbao Tunnel on ChengduLanzhou Railway
Launching and Receiving Technology of Large Crosssection Horseshoeshaped Shield Used in Baicheng Tunnel
Design and Analysis of a New TBM Propulsion System with Small Turning Radius
Study on Key Technologies and Application of Engineering Big Data Management Platform of Tunnel Boring Machine
Improvement Technology of Bearing Capacity of Prestressed Anchor Cable in Large span Tunnel: a Case Study on Badaling Great Wall Station