Construction Technologies for Threebenchsevenstep Excavation Method and Equipment Matching of Soft Rock Tunnel on BaojiLanzhou Passengerdedicated Railway Line

DAI Runjun, LI Dongshun, ZHANG Chengyong   

  1. (The Second Engineering Co., Ltd. of China Railway Tunnel Group, Sanhe 065201, Hebei, China)
  • Received:2015-05-24 Revised:2015-07-02 Online:2015-12-15 Published:2015-12-24

Abstract:

In this paper, the construction keys and equipment matching of threebenchsevenstep excavation method used in construction of Guchengling Tunnel and Lanshan Tunnel on BaojiLanzhou passengerdedicated railway line are presented. The suggestions for the construction are proposed as well.

Key words: BaojiLanzhou passengerdedicated railway line, threebenchsevenstep excavation method, mechanization, invert, step distance, soft rock tunnel