Risk Analysis and Countermeasures for Excavation of Deep  Foundation Pit in Waterrich Composite Strata

ZHU Yuhong1, 2, CHEN Juwu1, 2, MA Hui1, 2, ZHAI Lihua2, 3, *   

  1. (1. Guangzhou Metro, Guangzhou 510335, Guangdong, China;  2. National Engineering Laboratory for Urban Rail Transit System Security and Maintenance Support,  Guangzhou 510335, Guangdong, China;  3. Guangzhou Metro Design & Research Institute Co., Ltd., Guangzhou 510010, Guangdong, China)
  • Received:2017-09-08 Revised:2018-08-28 Online:2018-09-20 Published:2018-09-30

Abstract:

The construction risk of deep metro foundation pit in waterrich composite strata is high, and there is little relevant research. Hence, the characteristics and risk of excavation of deep metro foundation pit in waterrich composite strata are summarized based on risk source analysis and construction experience of Guangzhou Metro; and the construction method of "excavation and assessment, presealing, defect repairing, scientific dewatering, uniform and adequate backfilling, accurate measurement, timely support and rapid construction" is proposed and introduced. The abovementioned method emphasizes the integrality and waterproofing capacity of the retaining structure, richwater risk and successful completion of highrisky construction procedure. The method takes the risk assessment as the basis and the countermeasure preposition as the core, by doing which the risk of deep foundation pit construction in waterrich composite strata can be effectively controlled.

Key words: waterrich composite strata, deep foundation pit, metro project, risk analysis, risk countermeasure