ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2019, Vol. 39 ›› Issue (S2): 318-325.DOI: 10.3973/j.issn.2096-4498.2019.S2.040

Previous Articles     Next Articles

Key Design Technologies for Cut and Cover Cofferdam of Wenming East Road Tunnel in Haikou

ZHANG Huirong, XIE Qiaomu   

  1. (CCCC-FHDI Engineering Co., Ltd., Guangzhou 510230, Guangdong, China)
  • Received:2019-04-16 Online:2019-12-31 Published:2020-04-04

Abstract:

Based on the hydrological, tidal, and geological characteristics of the Nandu River and the characteristics of the Wenming East Road Tunnel project, the key design technologies of section, stage and elevation of cofferdam and depth of tunnel are analyzed. The design schemes of cofferdam and foundation pit are compared in terms of flood control evaluation, construction period and cost. The study shows that: (1) The rational determination of cofferdam layout scheme and construction period is the key to the success of the project. (2) Compared to double-row pile, the structural internal force, deformation and settlement by adopting the large excavation scheme with both sides of the slope are much smaller, and the cofferdam structure is safer, which can greatly shorten the construction period and save the project cost.

Key words: river-crossing tunnel, interception, cut and cover cofferdam, foundation pit support

CLC Number: