Tunnel Construction ›› 2020, Vol. 40 ›› Issue (10): 1525-1532.DOI: 10.3973/j.issn.2096-4498.2020.10.017

Previous Articles     Next Articles

Demolition of Temporary Support and Rapid Construction Technology of Secondary Lining Structure in Super Large Crosssection Mined Cavern: a Case Study on Shenzhen Foreign Languages School Station on Shenzhen Metro Line 8

WANG Shuaishuai1, 2, CAI Tangtao1, WU Chun1, XU Qianshun1, GAO Bo2   

  1. (1. CCCC Second Highway Engineering Co., Ltd., Xian 710056, Shaanxi, China; 2. Southwest Jiaotong University, Chengdu 610031, Sichuan, China) 
  • Online:2020-10-20 Published:2020-11-01

Abstract:

A mined station and the connecting line secondary lining of Shenzhen Foreign Languages School Station on Shenzhen Metro Line No. 8 are characterized by super large crosssection, complex dismantling technology and difficult construction organization. To overcome these problems, the lining face in tunnel is optimized to 4 to reach smooth construction organization based on construction organization of 7 working faces and the castinplace scheme of vertical multilayer support and considering the construction site conditions, schedule node arrangement and construction organization mode. And with the application of large crosssection secondary lining trolley, the number of vertical layered pouring and the workload of support formwork has been reduced, and the overall construction progress has been accelerated. Finally, based on the finite element numerical simulation, the deformation law of the supporting structure in the whole process of excavation, demolition of temporary support and construction of secondary lining of the super large crosssection mining project is analyzed, and the analytical results coincide with the actual conditions well, indicating that the deformation is within control. By optimizing the construction organization and adopting the secondary lining trolley, the construction progress has been greatly improved on the premise of ensuring safety and quality, the construction period has been saved by 52 days, and the construction cost has been reduced by RMB1.15 million yuan.

Key words: super large crosssection, metro station, connecting line, mining method, temporary support demolition, secondary lining