Abstract: The jacking force of rectangular pipe jacking machine is an important parameter in jacking design, but there is no unified standard calculation formula at present. In this paper, the Bill Bowman theory and the theory of partial contact between pipe soil and slurry are modified and improved, and the shell frictional resistance of pipe jacking machine is calculated separately, based on which a new method for calculating the jacking force of rectangular pipe jacking machine with large crosssection is deduced. The comparative analysis is made between calculated value and the measured value of jacking force of the largesection rectangular pipe jacking machine used in Suzhou Chengbei Road, and the results show that: (1) The Bill Bowman′s theory suits for upper earth pressure calculation better. (2) When a stable mud set is formed, the head resistance of 1.1 times of the static earth pressure is highly consistent with the actual situation. (3) The jacking force per unit length calculated by the derivation method is close to the measured value, and the engineering applicability is good.
Key words: large crosssection rectangular pipe jacking machine, Bill Bowman′s theory, mud set, jacking force
CLC Number:
U 452
XUE Qingsong. Calculation and Measurement Analysis of Jacking Force of Large Crosssection Rectangular Pipe Jacking Machine Used in Suzhou Chengbei Road[J]. Tunnel Construction, 2020, 40(12): 1717-1724.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.2096-4498.2020.12.005
http://www.suidaojs.com/EN/Y2020/V40/I12/1717
Calculation Method of Highway Tunnel Lighting Based on Bidirectional Reflectance Distribution Function and Energy Saving Measures
Parametric Modeling of Hatbrim Slanting Cut Tunnel Portal Based on MicroStation
Study on Mechanical Deformation of Shield Tunnel Crosssection under Eccentric Unloading of Side Foundation Pit Excavation