Analysis of Rockburst Characteristics of Deepburied Tunnel and Comprehensive Control Technology: a Case Study of Ping′an Tunnel on ChengduLanzhou Railway

LI Jiangao, TANG Zelin   

  1. (The 3rd Engineering Co., Ltd., China Railway Tunnel Group, Shenzhen 518000, Guangdong, China)
  • Online:2020-12-20 Published:2021-01-03

Abstract: It is of great importance to effectively control the dynamic instability and continuous rockburst of the surrounding rock of deepburied tunnel under the influence of high ground stress, ensure the stability of surrounding rock, effective support structure and safety of construction personnel, and pass through the rockburst section with high ground stress smoothly and quickly. Therefore, the rockburst characteristics of Pingan Tunnel on ChengduLanzhou Railway are summarized, and the rockburst characteristics in different time periods, different tunnel locations, different levels and different tunnel segments are analyzed. Moreever, a comprehensive rockburst prevention and treatment measure combining prevention, control and monitoring is put forward from the aspects of technological method, blasting parameters, support structure and deformation monitoring, which can effectively control the construction risk of rockburst section of deepburied tunnel with high ground stress and realize safe and rapid construction.

Key words: deepburied tunnel, high ground stress, rockburst characteristics, prevention measures, optimized construction