Water Gushing Treatment Technology for Deep and Large Vertical Shafts of Railway in Waterrich Weathered Granite: a Case Study on #1 Vertical Shaft of Gaoligongshan Tunnel on DaliRuili Railway

GAO Guangyi1, 2   

  1. 1. China Railway Tunnel Consultants Co., Ltd., Guangzhou 511457, Guangdong, China; 2. Key Laboratory of Intelligent Monitoring and Maintenance of Tunnel Structure, CRTG, Guangzhou 511457, Guangdong, China
  • Online:2020-08-30 Published:2020-09-14

Abstract: In order to solve the problem of water inrush and flooding during the construction of superdeep railway shafts in waterrich weathered granite areas, the construction of #1 shaft in Gaoligongshan Tunnel on DaliRuili Railway characterized by complex geological conditions, waterrich and high pressure, small working face and difficult water drainage is taken as an example to study the technologies of detection and grouting at working face, drilling in small space and grouting of vertical shaft. Furthermore, the construction principle of excavation with detection, waterstop as mainand stopdrainage combination and gushing water treatment measure of pregrouting at working face and grouting behind shaft wall are put forward for superdeep vertical shaft construction of railway in waterrich granite area, which can effectively control the water gushing and improve the construction efficiency of shaft construction.

Key words: railway tunnel, waterrich granite, vertical shaft, gushing water treatment