Abstract: When an earth pressure balance shield tunneling in a longdistance section with high quartz content, the screw conveyor jammed and hysteretic mucking occurred. Hence, the causes for screw conveyor malfunction are analyzed, countermeasures are proposed for hysteretic mucking, and corresponding repairing methods are determined, resulting in a good effect. Furthermore, according to the hard rock conditions, an optimized scheme for hydraulic system and treatments for screw conveyor jamming are proposed, and the suitable driving technological parameters and rational bentonite ratio are obtained through test. The countermeasures recommended successfully release the screw conveyor and guarantee the highefficient operation of the equipment onsite.
Key words: shield machine, hard rock formations, screw conveyor, hysteretic mucking, longdistance boring
LI Gongyi. Fault Analysis and Countermeasures for Screw Conveyor of Earth Pressure Balance Shield Boring in LongDistance Hard Rock Section[J]. Tunnel Construction, 2022, 42(S2): 502-507.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.2096-4498.2022.S2.063
http://www.suidaojs.com/EN/Y2022/V42/IS2/502
Study of Muck Discharging Volume of Screw Conveyor of Earth Pressure Balance Shield Based on Bingham Fluid
Model Test Verification of Synchronous Technology Combining Shield Tunneling with Segment Assembling Based on Principle of Uniform Loading on a Single Segment
Detection and Cause Analysis of Main Drive Seal Failure of Shield Machine