ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2023, Vol. 43 ›› Issue (7): 1127-1138.DOI: 10.3973/j.issn.2096-4498.2023.07.005

Previous Articles     Next Articles

Pollutant Diffusion Law in Relay Ventilation of Long Ventilation Chamber  in Wushan Tunnel on ZhengzhouWanzhou HighSpeed Railway

JIAO Hongwei   

  1. (No.1 Engineering Co., Ltd. of China Railway 18th Bureau Group, Baoding 072750, Hebei, China)
  • Online:2023-07-20 Published:2023-08-06

Abstract:

 During the construction of the Wushan extralong tunnel, several environmental problems emerged. These included the large release of pollutants in the working space, inefficiency in replacing sewage wind, and dangerous local concentration of harmful gases. To address these challenges, the dynamic diffusion law of pollutants such as CO and dust is examined. This analysis is based on field monitoring data and employs a fullscale numerical simulation method. Moreover, the hindering effect of lining trolleys on dust diffusion is explored under various conditions, including singlehole tunneling, doublehole synergistic tunneling, and within a long ventilation chamber. The results reveal the following findings: (1) The air flow field stability is affected by the longitudinal return air velocity of the tunnel, leading to relatively large fluctuations in the air flow field within the 0.5~0.7 m/s range, hindering the pollutants discharge. (2) Pollutant is ultimately discharged synchronously by decreasing the overall concentration when CO diffuses. The 900 s ventilation proves sufficient for the allowable CO concentration within 200 m of the working face during both single and doublehole tunneling conditions. (3) The presence of a trolley has a remarkable blocking effect on the blasting dust diffusion, resulting in an approximate 42% lower overall dust reduction rate in the section with secondary lining trolleys compared to the construction section without the trolleys. Moreover, the dust reduction efficiency without a trolley is approximately 2.5 times higher than that with a trolley.

Key words: extralong railway tunnel, construction ventilation, field test, numerical simulation, pollutant diffusion