ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2015, Vol. 35 ›› Issue (2): 185-190.DOI: 10.3973/j.issn.1672-741X.2015.02.014

Previous Articles     Next Articles

Saturated Hyperbaric Operation under Compressed Air: Case Study on Construction of Weisanlu Rivercrossing Tunnel by Largediameter Slurry Shield

YAO Zhanhu1, CHEN Fangwei2, CHEN Yu1   

  1. (1 CCCC Tunnel Engineering Co, Ltd, Beijing 100088, China; 2 CCCC Investment Company Ltd, Beijing 100029, China)
  • Received:2014-10-08 Revised:2014-11-05 Online:2015-02-20 Published:2015-02-11

Abstract:

The existing hyperbaric operation technologies in tunneling by largediameter slurry shields under complex hydrogeological conditions and complex environment have some disadvantages In the construction of Weisanlu rivercrossing tunnel in Nanning, China, the shield boring has to be suspended to perform repair and maintenance of the cutterhead As a result, the technology of saturated hyperbaric operation under compressed air is proposed In this paper, the geological conditions of the tunnel where the shield stops are studied on basis of the geological prospection report, the working principle of saturated hyperbaric operation under compressed air is presented, the calculation of the pressure at the tunnel face in introduced, and the forming of the airtight filter membrane, the equipment and working procedure of saturated hyperbaric operation under compressed air are expounded The practice shows that the mentioned technology can ensure the successful inspection and replacement of the cutting tools of shield machines under complex conditions, and it can improve the adaptability of shield machines to complex geological conditions

Key words: compressed air, largediameter slurry shield, hyperbaric operation, saturation method

CLC Number: