Pilenet composite foundation treatment method is adopted for the soft ground of Baishi bridge on Junda highway on basis of the actual conditions of the works. The consolidation mechanisms of pilenet composite foundations are discussed. The layout of the piles is executed on basis of the singlepile bearing capacity calculation results. Items to which attention should be paid during piling are expatiated. Countermeasures are provided for the piping occurring during construction.
CLC Number:
 
U445.55
DONG Xiaomei, LI Haixia. Soft Ground Treatment for Baishi Bridge on Junda Highway[J]. Tunnel Construction, 2008, 28(2): 237-239.