ISSN 2096-4498
CN 44-1745/U
Tunnel Construction ›› 2007, Vol. 27 ›› Issue (增刊): 229-232.DOI: B
• wenzhang • Previous Articles Next Articles
CHEN Kui, HAN E-Li
Received:
Revised:
Online:
Published:
Abstract:
Shiziyang tunnel on the GuangzhouShenzhenHongkong passenger line is constructed using the shield machines, and it is the first tunnel that shield machines go and meet underneath water in a long distance in China. The design of shield machine that can be used under the geological conditions in the lot SDIII is presented, and the technology of meeting of shield machines in the tunnel is also introduced in this paper.
Key words: passenger line  , design of shield machine  , meeting of shield machines in the tunnel
CLC Number:
U455.3+9
CHEN Kui, HAN E-Li. Design and Construction of Shiziyang Shield Tunnel on Passenger Line[J]. Tunnel Construction, 2007, 27(增刊): 229-232.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2007/V27/I增刊/229