ISSN 2096-4498

   CN 44-1745/U

二维码
wenzhang

Tunneling in Mud/Sand Bursting Geology by Singleshield TBM

Expand
  • (China Railway Tunnel Stock Co., Ltd., Zhengzhou 450001, China)

Received date: 2011-11-15

  Revised date: 2011-12-30

  Online published: 2012-03-09

Abstract

No. 7 tunnel of the first phase of Tao River Diversion Project in Gansu Province is excavated by a singleshield TBM. During the construction of the tunnel, water/mud/sand bursting occurs. Countermeasures, including advance geology prediction, backfilling grouting for gaps behind the segment, advance consolidation grouting and water/sand releasing after diluting, are taken to cope with the situation. 

Cite this article

GAO Kun . Tunneling in Mud/Sand Bursting Geology by Singleshield TBM[J]. Tunnel Construction, 2012 , 32(1) : 94 -98 . DOI: 10.3973/j.issn.1672-741X.2012.01.016

Outlines

/

〈 〉