Analysis on Construction of Connection Gallery at  WSS Grouting Reinforcement Section of Xi’an Metro

  • LIU Dan
Expand
  • (Urban Rail Department of China Railway First Group Co., Ltd., Xi’an 710000, China)

Received date: 2012-06-19

  Revised date: 2012-08-20

  Online published: 2013-02-19

Abstract

The traditional method can not guarantee the construction of connection gallery in Xi’an Metro. The WSS grouting reinforcement methods in tunnel are proposed. The keys of the mentioned method are the position of the grouting holes and the grouting matching and parameters. The paper can provide references for the construction of connection gallery of Xi’an Metro.

Cite this article

LIU Dan . Analysis on Construction of Connection Gallery at  WSS Grouting Reinforcement Section of Xi’an Metro[J]. Tunnel Construction, 2012 , 32(增刊1) : 79 -84 . DOI: 10.3973/j.issn.1672-741X.2012.z1.017