Rapid Drilling of Retaining pile Hole for Deep Pit in Hard Rock
Received date: 2012-07-26
Revised date: 2012-09-10
Online published: 2013-02-19
According to the construction experiences of rotatory drill pile for the retaining structure of the pit at Tiyugongyuan station on No. line of Changsha metro, the associated application of rotatory drill and downthehole drill in the construction of retaining structure for deep metro pit is presented in this paper.
ZHU Zhensheng . Rapid Drilling of Retaining pile Hole for Deep Pit in Hard Rock[J]. Tunnel Construction, 2012 , 32(增刊2) : 136 -140 . DOI: 10.3973/j.issn.1672-741X.2012.z2.027
/
| 〈 |
|
〉 |