Case Study on Installation of Shaped Steel Columns in Highstrength Rocks in Construction of Chegongmiao Station of Line  11  of Shenzhen Metro

  • CHEN Yu ,
  • LI Hailong
Expand
  • (The Third Engineering Co, Ltd of China Railway Tunnel Group, Shenzhen 518052, Guangdong, China)

Received date: 2013-11-27

  Revised date: 2014-03-11

  Online published: 2014-04-25

Abstract

In the construction of Chegongmiao Station of 11301 bid section of Line 11 of Shenzhen Metro, shaped steel columns need to be installed rapidly and accurately into highstrength rocks (with 120 MPa uniaxial compressive strength) The following two key technologies are adopted to fulfill the difficult job: 1) Advanced coretaking drilling rig is used and special core taking process is adopted so that large diameter (with 20 m diameter) boreholes can be drilled rapidly in the highstrength rocks (with 15~20 m cyclic drilling rate); 2) The method of installing the crossshaped steel columns after concrete casting is used so that the shaped steel columns can be installed rapidly and accurately In the end, the job has been fulfilled successfully

Cite this article

CHEN Yu , LI Hailong . Case Study on Installation of Shaped Steel Columns in Highstrength Rocks in Construction of Chegongmiao Station of Line  11  of Shenzhen Metro[J]. Tunnel Construction, 2014 , 34(4) : 362 -367 . DOI: 10.3973/j.issn.1672-741X.2014.04.012

Outlines

/

〈 〉