In the construction of Chegongmiao Station of 11301 bid section of Line 11 of Shenzhen Metro, shaped steel columns need to be installed rapidly and accurately into highstrength rocks (with 120 MPa uniaxial compressive strength) The following two key technologies are adopted to fulfill the difficult job: 1) Advanced coretaking drilling rig is used and special core taking process is adopted so that large diameter (with 20 m diameter) boreholes can be drilled rapidly in the highstrength rocks (with 15~20 m cyclic drilling rate); 2) The method of installing the crossshaped steel columns after concrete casting is used so that the shaped steel columns can be installed rapidly and accurately In the end, the job has been fulfilled successfully
Key words: Metro station, highstrength rock, rapid borehole drilling, crossshaped steel column, method of installing steel columns before concrete casting, method of installing steel columns after concrete casting, accurate positioning
CHEN Yu, LI Hailong. Case Study on Installation of Shaped Steel Columns in Highstrength Rocks in Construction of Chegongmiao Station of Line 11 of Shenzhen Metro[J]. Tunnel Construction, 2014, 34(4): 362-367.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2014.04.012
http://www.suidaojs.com/EN/Y2014/V34/I4/362