ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2014, Vol. 34 ›› Issue (4): 362-367.DOI: 10.3973/j.issn.1672-741X.2014.04.012

Previous Articles     Next Articles

Case Study on Installation of Shaped Steel Columns in Highstrength Rocks in Construction of Chegongmiao Station of Line  11  of Shenzhen Metro

CHEN Yu, LI Hailong   

  1. (The Third Engineering Co, Ltd of China Railway Tunnel Group, Shenzhen 518052, Guangdong, China)
  • Received:2013-11-27 Revised:2014-03-11 Online:2014-04-20 Published:2014-04-25

Abstract:

In the construction of Chegongmiao Station of 11301 bid section of Line 11 of Shenzhen Metro, shaped steel columns need to be installed rapidly and accurately into highstrength rocks (with 120 MPa uniaxial compressive strength) The following two key technologies are adopted to fulfill the difficult job: 1) Advanced coretaking drilling rig is used and special core taking process is adopted so that large diameter (with 20 m diameter) boreholes can be drilled rapidly in the highstrength rocks (with 15~20 m cyclic drilling rate); 2) The method of installing the crossshaped steel columns after concrete casting is used so that the shaped steel columns can be installed rapidly and accurately In the end, the job has been fulfilled successfully

Key words: Metro station, highstrength rock, rapid borehole drilling, crossshaped steel column, method of installing steel columns before concrete casting, method of installing steel columns after concrete casting, accurate positioning