Installing Replacement Bracing or Cancelling Replacement Bracing: Case Study on Deep Foundation Pit of Xiwang Station of Line  1 of Shijiazhuang Metro

  • TANG Qi ,
  • WANG Huamin
Expand
  • (Shanghai Civil Engineering Group Co., Ltd of CREC, Shanghai 200436, China)

Received date: 2015-04-20

  Revised date: 2015-06-09

  Online published: 2015-08-17

Abstract

The foundation pit of Xiwang station of Line 1 of Shijiazhuang Metro is located in collapsible loess strata. In the paper, theoretical analysis is made on the foundation pit on basis of the actual geological and hydrogeological conditions and it is proposed that the originallydesigned replacement bracing could be cancelled, while full scaffold should be installed to support the structure. The proposal has been applied in the construction of the Metro station and good effects have been achieved. 

Cite this article

TANG Qi , WANG Huamin . Installing Replacement Bracing or Cancelling Replacement Bracing: Case Study on Deep Foundation Pit of Xiwang Station of Line  1 of Shijiazhuang Metro[J]. Tunnel Construction, 2015 , 35(S1) : 85 -92 . DOI: 10.3973/j.issn.1672-741X.2015.S1.017

Outlines

/

〈 〉