ISSN 2096-4498
CN 44-1745/U
ISSN 2096-4498
CN 44-1745/U
Application of Largediameter Hard Rock Tunnel Boring Machine (TBM) to TBM3 Section of No. 4 Bid of Songhua River Water Conveyance Project in Middle Jilin Province
Received date: 2015-11-25
Revised date: 2016-03-17
Online published: 2016-08-17
The characteristics and main design parameters of largediameter hard rock TBM used in No. 4 Bid Section of the Songhua River Water Conveyance Project are analyzed. The rock strata of the project are complicate; there are many fracture zones and limestone and quartz locally; and it requires highperformance of TBM cutterhead and cutting tools. As a result, the TBM cutterhead is manufactured by 270 mm thickness plate; the nonlinear distance among cutting tools is 82-90 mm; effective primary supporting system and material transportation platform are designed; and advance geology prediction system is adopted. The construction practice shows that the TBM cutterhead designed is reliable and highefficient; the supporting efficiency of TBM in bad geological conditions is high; and the advance geology prediction results are reliable.
HE fei , ZENG Xiangsheng , QI Zhichong . Application of Largediameter Hard Rock Tunnel Boring Machine (TBM) to TBM3 Section of No. 4 Bid of Songhua River Water Conveyance Project in Middle Jilin Province[J]. Tunnel Construction, 2016 , 36(8) : 1016 -1022 . DOI: 10.3973/j.issn.1672-741X.2016.08.019
/
| 〈 |
|
〉 |