The construction data of doubleshield TBM during construction of Qingdao Metro Line No. 2 in complex hard rocks are controlled and analyzed. The doubleshield TBM shows good adaptability to Qingdao Metro Tunnel. Meanwhile, countermeasures and suggestions are provide for small radius curve tunnel and doubleshield TBM in broken surrounding rocks based on construction practices.
SI Yudi . Study of Adaptability of Doubleshield TBM to Qingdao Metro[J]. Tunnel Construction, 2017 , 37(S1) : 212 -218 . DOI: 10.3973/j.issn.1672-741X.2017.S1.036
/
| 〈 |
|
〉 |