ISSN 2096-4498

   CN 44-1745/U

二维码

Development and Application of Equipment for Lateral Moving and Advancing without Load of TBM

  • ZHU Pengjin ,
  • ZHAO Kanglin ,
  • XIAO Lixing
Expand
  • (The 2nd Engineering Co., Ltd. of China Railway Tunnel Group, Sanhe 065201, Hebei, China)

Received date: 2019-08-19

  Online published: 2020-04-09

Abstract

The TBM used in Qingdao Metro Line No. 8 laterally moved and advanced without load for several times. As a result, a new type of hydraulic shifting equipment for full-face TBM is developed based on the disadvantages of lateral moving and advancing without load of TBM by "track first and then thrust" method, i. e. low efficiency, great amount of preparation, high precision requirement and great risk of process change. The gear system, eletrohydraulic control driving force and turning and guiding system are added to the equipment to improve the bearing capacity, driving force, gear strength, ground bearing capacity and planeness. The synchronous lateral moving and advancing without load of the TBM can be realized, the working process change time can be reduced, the working efficiency can be improved and the construction risk can be reduced by using the equipment. The results can provide reference for similar shield/ TBM tunneling projects in the future.

Cite this article

ZHU Pengjin , ZHAO Kanglin , XIAO Lixing . Development and Application of Equipment for Lateral Moving and Advancing without Load of TBM[J]. Tunnel Construction, 2020 , 40(3) : 417 -425 . DOI: 10.3973/j.issn.2096-4498.2020.03.015

Outlines

/

〈 〉