The mechanized construction method for connecting
passages can be divided into shield and pipe jacking methods. To clarify the
difference between mechanical and freezing methods, the structural
characteristics and safety, environmental influence, construction efficiency,
and energy consumption of the 21 connecting passages of shield tunnel of Ningbo
rail transit line 4 are analyzed.Analytical results demonstrate the following.
(1) The main tunnel structures constructed using different construction methods
are uniform to guarantee the standardization of the main tunnel structures. (2)
Various construction methods can meet relevant structural functions, structural
safety, and environmental requirements. (3) The convergence deformation of the
main tunnel obtained using the mechanical method is smaller than that obtained
using the freezing method, which promotes structural safety. (4) Under the same
conditions, the mechanical method requires approximately half the time of the
freezing method. Moreover, the power consumption per linear meter of connecting
passages obtained using the mechanical method is onetenth
of that obtained using the freezing method.
YAO Yanming
,
HUANG Yi
,
ZHOU Junhong
,
XIA Hanyong
. Construction Methods for Connecting Passages in Shield
Tunnel of Ningbo Rail Transit Line 4[J]. Tunnel Construction, 2021
, 41(6)
: 1007
-1014
.
DOI: 10.3973/j.issn.2096-4498.2021.06.013