Technology and Application of Temporary Invert With Detachable Components in Tunnels

  • CHEN Shihao ,
  • DAI Qinghua ,
  • CHEN Peishuai ,
  • YUAN Qing ,
  • XIONG Qihuan ,
  • YANG Zhao
Expand
  • (1. CCCC Second Harbor Engineering Company Ltd., Wuhan 430040, Hubei, China; 2. Key Laboratory of Large-span Bridge Construction Technology, Wuhan 430040, Hubei, China)

Online published: 2023-11-08

Abstract

The traditional temporary invert constructed by Isteel + shotcrete is complex in the construction process. Moreover, its construction quality is greatly affected by human factors and cannot be reused. Therefore, a novel detachable concretefilled steel tube temporary invert and its supporting structure, designed for easy and rapid disassembly, are proposed. The structures are tested and applied to the highspeed Zongka #2 tunnel of the TongrenSai′erlong railway. The steel pipe has an outer diameter of 108 mm and a wall thickness of 8 mm, and is filled with C30 fine stone concrete. The detachable components comprise a sleeve and a builtin wedgeshaped unloading block, and the concretefilled steel tubes are inserted from both sides to achieve segment connection. Field application results reveal the following: (1) The proposed temporary invert structure is safe, reliable, and feasible and can realize factory prefabrication and quick disassembly on site. The proposed temporary invert can improve construction efficiency by 643% and reduce the settlement deformation rate of the arch and peripheral convergence rate by 657%~661% and 746%~795%, respectively, compared to the traditional temporary invert constructed by I-steel + shotcrete. (2) The axial force value measured during the operation of the structure is less than the calculated and designed ones, indicating that the structure is in a safe state. The reutilization rates of the segment and detachable structure are up to 94.5% and 100%, respectively.

Cite this article

CHEN Shihao , DAI Qinghua , CHEN Peishuai , YUAN Qing , XIONG Qihuan , YANG Zhao . Technology and Application of Temporary Invert With Detachable Components in Tunnels[J]. Tunnel Construction, 2023 , 43(10) : 1779 -1787 . DOI: 10.3973/j.issn.2096-4498.2023.10.014

Outlines

/

〈 〉